Construction Procedure

圖片2.png
Based on the design drawings of the structure, first draw a sample drawing and submit it for review and confirmation.
On-site lofting measurement and drawing construction drawings and stone processing drawings.
Material inspection of stone samples is submitted for review.
The rough/slab is subject to factory inspection and confirmation.
The fixed material samples are submitted for review above the joint-filling materials.
According to the drawings, the stone slab produced by the factory is produced.
Ship to the designated location within the scheduled time limit.
Start construction and combined installation, then confirm the baseline and clean up the construction surface.
clean
Completion acceptance